First, construction scale and major construction elements: the first batch is to afforest and maintain quarry; the second batch is afforesting of 12 quarry and the construction of coastal mangroves, industrial shelterbelts, seawall primary forest, the forest fire pool, fire zone and green homes Fung Shui Woodland and Forest Village building, and the afforesting along subway and other projects
Second, the construction period: 2006-2008.
Third, the total investment and capital structure: the total investment is 504 million Yuan.
Fourth, project progress and the investment plan of 2007: the conservation of green, green-field rehabilitation work in quarry are going on. At the end of 2006, the total investment is 330 million Yuan and in 2007 the planned investment is 140 million Yuan.