First, construction scale and major construction elements: the shipbuilding capacity is 2.12 million dwt, and program products fare large container ships and large oil tankers, vessels and other large-scale ore, with the largest construction 300,000-ton ship capacity; major new two large shipyards, supporting 600 tons four gantry crane trucks, and the corresponding terminals, factories and other production facilities.
Second, the construction period: 2006-2009.
Third, the total investment and capital structure: the total investment 5.866 billion yuan, of which 4.33 billion yuan in fixed assets investment.
Fourth, project progress and the investment plan of 2007: At the end of 2006, the total investment is 510 million Yuan and in 2007 the planned investment is 180 billion Yuan.
Fifth , the forecast benefits: After the completion of project, it is significant to the development of Nansha port industry, promotion of economic development in Guangzhou, improvement of China's shipbuilding industry's overall competitiveness, and promotion of the development of China's shipbuilding industry.